Minutes of the September 1 2005 US Rod TV meeting



Follow up on action items from Aug 23 Workshop


FNAL status
Tested 10 more solution 6 rods on SRT.  One fails 2nd redundancy test consistently. 
Also seem to see more noise than usual in SRT.

Almost all new rods burnt in at MRT.  One failing module (!)

Took pictures of CLK and CTRL lines, look good. 
Want to test with benchtop PS instead of Delphi PS, although this had been done at UCSB with Guido and Wim.

Wim compiling Lt V30.  Will try asap, thne Wim gone for 2 weeks.

Frederic working on FEC SW.  Problem: V3 needs new gcc.  Considering upgrade of OS.....


UCSB status
Steve working on XML  files.  Guiilame responding to emails.

More on Spares
Spare TPO and TSC coming from CERN in September.  Riverside has TSC in case of emergency.  TPO might be a problem.