UCSB SVT Assembly Projection
Task Name |
Duration |
Projected Start |
Projected Finish |
Percent_Complete |
Receive HDIs |
33 days |
03-Sep-98 |
20-Oct-98 |
100% |
H1 Batch 1a (3 HDIs) |
3 hrs |
03-Sep-98 |
03-Sep-98 |
100% |
H1 Batch 1b (5 HDIs) |
3 hrs |
14-Sep-98 |
14-Sep-98 |
100% |
H1 Batch 1c (3 HDIs) |
3 hrs |
21-Sep-98 |
21-Sep-98 |
100% |
H1 Batch 2 (5 HDIs) |
3 hrs |
28-Sep-98 |
28-Sep-98 |
100% |
H1 Batch 3 (8 HDIs) |
3 hrs |
02-Oct-98 |
02-Oct-98 |
100% |
H1 Batch 4 (8 HDIs) |
3 hrs |
05-Oct-98 |
05-Oct-98 |
100% |
H2 Batch 1 (4 HDIs) |
3 hrs |
22-Sep-98 |
22-Sep-98 |
100% |
H2 Batch 2 (4 HDIs) |
3 hrs |
06-Oct-98 |
06-Oct-98 |
100% |
H2 Batch 2 (8 HDIs) |
3 hrs |
13-Oct-98 |
13-Oct-98 |
100% |
DFA Bonding |
88.5 days |
11-Mar-98 |
16-Jul-98 |
100% |
HDFA Assembly |
90.6 days |
03-Sep-98 |
20-Dec-98 |
89% |
Layer 1 Type A |
69.1 days |
03-Sep-98 |
08-Dec-98 |
100% |
Layer 2 Type A |
53.89 days |
03-Sep-98 |
19-Nov-98 |
100% |
Layer 3 Type A |
63.2 days |
22-Sep-98 |
20-Dec-98 |
67% |
2 Layer 3 Type C |
3 days |
19-Oct-98 |
21-Oct-98 |
100% |
Sextant Assembly |
56.2 days |
29-Sep-98 |
18-Dec-98 |
83% |
Sextant 1 |
4 days |
29-Sep-98 |
02-Oct-98 |
100% |
Sextant 2 |
4 days |
07-Oct-98 |
13-Oct-98 |
100% |
Sextant 3 |
4 days |
02-Nov-98 |
06-Nov-98 |
100% |
Sextant 4 |
4 days |
24-Nov-98 |
01-Dec-98 |
100% |
Sextant 5 |
4 days |
04-Dec-98 |
11-Dec-98 |
100% |
Sextant 6 |
4 days |
14-Dec-98 |
18-Dec-98 |
0% |
2 Layer 3 Type C Modules |
4 days |
26-Oct-98 |
29-Oct-98 |
100% |
Layer 3 Assembly |
46 days |
02-Nov-98 |
14-Jan-99 |
33% |
Layer 3 Module 1 |
2 days |
02-Nov-98 |
03-Nov-98 |
100% |
Layer 3 Module 2 |
2 days |
17-Nov-98 |
18-Nov-98 |
100% |
Layer 3 Module 3 |
2 days |
21-Dec-98 |
22-Dec-98 |
0% |
Layer 3 Module 4 |
2 days |
05-Jan-99 |
06-Jan-99 |
0% |
Layer 3 Module 5 |
2 days |
08-Jan-99 |
11-Jan-99 |
0% |
Layer 3 Module 6 |
2 days |
13-Jan-99 |
14-Jan-99 |
0% |
Last Updated on 12/11/98
By Philip Hart