UCSB SVT Assembly Projection

Task Name Duration Projected Start Projected Finish Percent_Complete
Receive HDIs 33 days 03-Sep-98 20-Oct-98 100%
H1 Batch 1a (3 HDIs) 3 hrs 03-Sep-98 03-Sep-98 100%
H1 Batch 1b (5 HDIs) 3 hrs 14-Sep-98 14-Sep-98 100%
H1 Batch 1c (3 HDIs) 3 hrs 21-Sep-98 21-Sep-98 100%
H1 Batch 2 (5 HDIs) 3 hrs 28-Sep-98 28-Sep-98 100%
H1 Batch 3 (8 HDIs) 3 hrs 02-Oct-98 02-Oct-98 100%
H1 Batch 4 (8 HDIs) 3 hrs 05-Oct-98 05-Oct-98 100%
H2 Batch 1 (4 HDIs) 3 hrs 22-Sep-98 22-Sep-98 100%
H2 Batch 2 (4 HDIs) 3 hrs 06-Oct-98 06-Oct-98 100%
H2 Batch 2 (8 HDIs) 3 hrs 13-Oct-98 13-Oct-98 100%
DFA Bonding 88.5 days 11-Mar-98 16-Jul-98 100%
HDFA Assembly 90.6 days 03-Sep-98 20-Dec-98 89%
Layer 1 Type A 69.1 days 03-Sep-98 08-Dec-98 100%
Layer 2 Type A 53.89 days 03-Sep-98 19-Nov-98 100%
Layer 3 Type A 63.2 days 22-Sep-98 20-Dec-98 67%
2 Layer 3 Type C 3 days 19-Oct-98 21-Oct-98 100%
Sextant Assembly 56.2 days 29-Sep-98 18-Dec-98 83%
Sextant 1 4 days 29-Sep-98 02-Oct-98 100%
Sextant 2 4 days 07-Oct-98 13-Oct-98 100%
Sextant 3 4 days 02-Nov-98 06-Nov-98 100%
Sextant 4 4 days 24-Nov-98 01-Dec-98 100%
Sextant 5 4 days 04-Dec-98 11-Dec-98 100%
Sextant 6 4 days 14-Dec-98 18-Dec-98 0%
2 Layer 3 Type C Modules 4 days 26-Oct-98 29-Oct-98 100%
Layer 3 Assembly 46 days 02-Nov-98 14-Jan-99 33%
Layer 3 Module 1 2 days 02-Nov-98 03-Nov-98 100%
Layer 3 Module 2 2 days 17-Nov-98 18-Nov-98 100%
Layer 3 Module 3 2 days 21-Dec-98 22-Dec-98 0%
Layer 3 Module 4 2 days 05-Jan-99 06-Jan-99 0%
Layer 3 Module 5 2 days 08-Jan-99 11-Jan-99 0%
Layer 3 Module 6 2 days 13-Jan-99 14-Jan-99 0%

Last Updated on 12/11/98
By Philip Hart